K Rail Work
DATE AND WORK HOUR
• Removal and Installation of K-Rail: Friday, May 15, 2026, 8pm, through Monday, May 18, 2026, 6am
• Pacoima Box Culvert Replacement: Monday, May 18, 2026, through November 30, 2026
• Monday to Saturday: Day Shift: 6am to 2pm and Night Shift 8pm to 6am LOCATION: Van Nuys Bl between Vanowen St. to Arminta St.
WHAT TO EXPECT
- A directional street closure will be implemented on Van Nuys Bl between Vanowen St and Arminta St to facilitate the removal of the K-rail on the east side of the street and installation of new k-rail along the Pacoima Wash. The road will have lane restrictions on the northbound and southbound directions during the weekend closures. Some side streets will be impacted with traffic restrictions during work hours.
- Flaggers will be provided at various locations to direct traffic and pedestrians if access is restricted. The sidewalk will remain open during construction.
- Parking may be restricted in posted areas. Please follow the signage with the restrictions and avoid possible citations or towing.
- Bus stops may be temporarily relocated as necessary, please follow the signage.
K Rail Notice UA2-3 Notice Restoration and Pacoima Box Culvert_REV01
Utility Work
SUMMARY
Metro’s contractor will perform utility investigation along the project corridor. This work will include potholing operations and will require traffic lane closures along the project corridor on Van Nuys Bl between Oxnard St and Hamlin St. Work to be performed here will include traffic control, potholing operations, and street restoration. The upcoming work includes the full closures on the west and east side of Calvert St, Delano St, Erwin St, Sylvan St and Friar St. Please note both sides of the streets listed will not be closed at the same time. Each side will last one to two days for the pothole investigation work. In addition, Oxnard St and Hamlin St will have lane restrictions during the work.
WORK SCHEDULE
Nightly: Monday-Friday from 8pm to 6am. Anticipated schedule for all work activities is May 4 to June 17, 2026, below please see
the proposed schedule. Weather permitting. Schedule is subject to change:
• West Oxnard St- May 4 to May 5, 2026
• East and West Delano St – May 6 to May 8, 2026
• East and West Calvert St – May 11 to May 14, 2026
• East and West Erwin St- May 15 to May 20, 2026
• East and West Sylvan St- May 21 to May 26, 2026
• East and West Friar St- May 27 to May 29, 2026
• East and West Hamlin St- May 30 to June 5, 2026
LOCATION
Traffic control on Van Nuys Blvd between Oxnard St and Hamlin St with full closures at Calvert St, Delano St, Erwin St, Sylvan St and
Friar St, and lane restrictions at Oxnard St and Hamlin St.
WHAT TO EXPECT
• Van Nuys Bl will remain open with lane restrictions between Oxnard St and Hamlin St.
• Access to private driveways, residences, and businesses will always be maintained unless notified in advance.
• The road will be fully reopened to vehicular traffic and parking daily after work hours.
• Flaggers will be provided at various locations to direct traffic and pedestrians if access is restricted.
• Parking is restricted in posted areas; please follow the signage to prevent a citation or towing
• Bus stops may be temporarily relocated as necessary. Please follow the signage.
Potholing_Notice_-Seg A1Oxnard to Hamlin Potholing Full Closure_V1- Final