closure areaMetro’s contractor, San Fernando Transit Constructors (SFTC), will conduct utility installations on the east side of Sherman Wy near the intersection of Van Nuys Bl requiring a full street closure on the east side. The work includes various traffic control implementations, pothole investigation, demolition, trench excavation, installation of conduit, duct banks, vaults, shoring and backfill, concrete and paving work.

December 15, 2025, to March 16, 2026
Monday to Friday 8pm to 6am, weather permitting.